Here's what's happening:
Work continues on the demolition of the old main entrance. Drilling holes in the floors (core drilling) will be done on all 3 floors to make way for the new electrical rooms and new bathrooms. A lot of work is being done in the maintenance area on the lower level to get the new server room ready. A street cleaning machine came through the parking lot late Friday to help clear up all the mud from last week's wet weather. The pile drilling machine completed 5 test holes last week. These piles are now being examined before the drilling of the 111 piles begin next week. The good news is this method of pile driving is not nearly as disruptive as we thought it would be. The installation of new duct work is nearly finished on the first floor and the dry walling of office space has begun. Unfortunately, the free coffee has ended for the semester.