Tuesday, January 23, 2007

Noise levels & Piles

Whiting Turner has informed the library that cutting for the new elevator shaft will begin tomorrow, Wednesday January 24th. This could possibly last until the end of next week.
The library will be very noisy as they will be using a humongous jackhammer. Construction usually stops at 3pm so it will be quiet after that.


The pile work outside the main entrance is going on now. As of January 16th, 36 of the 112 piles have been completed. The pile work should be finished by the first week in February.